Friday, August 31, 2007

31 August

A slight change of plan from last months anticipated actions. We did as planned put in the front framework around the cab, level and straighten the front bulkhead and support the remains of the cab. Alas not much more can be tackled here now until the upstairs goes in and provides the necessary support. So we decided to tackle the staircase and conductors area before moving on to the upstairs flooring, purely to make it easier to work on the floor and in addition to fit back a number of the original panels to make sure everything is fitting as it should!! As you can see the results are pretty good. All the panels that have gone back on are originals that were all in good condition and generally required sanding down and etching before going back into their rightful place. All the kick plates are again the originals and some of the wood supports are but alas most of the other wood was beyond re-use. Next month hopefully the flooring and last of the staircase will all be in place, unless of course we have another change of plan!






1 comment:

Anonymous said...

Just to keep you updated due to sickness and holidays around 3 weeks work was lost so a September update was pretty pointless. There will be an update the first week in November as the result of much work will start to be visual rather than lying in neat piles awaiting fixing to the bus!